Asphalt resurface project continues on U.S. 50 in Seymour

Indiana Department of Transportation contractor Dave O’Mara Contractors Inc. plans to conduct full/partial depth patching and resurfacing throughout each weekend in September, beginning today.

Work will take place along U.S. 50 from O’Brien Street to Agrico Lane in east and westbound lanes through Seymour.

Crews began patching work at approximately 4 a.m. today and are expected to complete patching work Sunday, weather permitting.

Following the completion of patching work, crews are scheduled to begin milling and paving on or after Friday. Milling and paving is expected to be complete by Sept. 17, weather permitting. All additional work will take place the following weekend.

Drivers should remain alert for changes in traffic patterns and expect message boards while work is in progress.

INDOT reminds motorists to slow down, use caution and drive distraction-free in and near work zones. All work is weather-dependent, and schedules are subject to change